Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Hinze Dam Stage 3 project.

Read more about project changes

Project change application 3 - Compensatory habitat land tenure arrangements

Date Activity
06 November 2014 Coordinator-General's report on project change (PDF icon 660 KB) released, approve the change.
30 September 2014 Proponent's project change application (PDF icon 1.2 MB) submitted.

Project change application 2 - Compensatory habitat land tenure arrangements

Date Activity
22 April 2010 Coordinator-General's report on project change (PDF icon 179 KB) released, approve the change.

Project change application 1 - Construction of cut-off wall

Date Activity
31 July 2008 Coordinator-General's report on project change (PDF icon 329 KB) released, approve the change.