Wetalla Water Pipeline
Project overview*
EIS status | Approved with conditions |
Description | A 45-kilometre underground water pipeline to supply up to 5500 megalitres of treated waste water to the New Acland coal mine, which is earmarked for expansion. |
Proponent | New Acland Coal Pty Ltd, a subsidiary of New Hope Corporation Limited |
Location/s | The pipeline will run from the Wetalla Wastewater Reclamation Facility in Toowoomba to the mine, 35 km north-west of the city. Map |
Local Government/s | Toowoomba Regional Council |
Key features |
|
* Project information supplied by proponent and subject to change.
Pipeline part of larger project
The Wetalla Water Pipeline is one of the components of the New Acland Coal Mine Stage 3 Expansion Project, which aims to expand the mine's production from 4.8 million tonnes per annum (mtpa) to up to 7.5 mtpa.
Construction of the water pipeline was expedited by the proponent, in accordance with section 32(1)(b) of the State Development and Public Works Organisation Act 1971.
This section of the Act allows proponents to prepare a separate environmental impact statement (EIS) that addresses the terms of reference relating to a particular component of the project.
Please note: although the water pipeline EIS is separate to the EIS for the remainder of the project, all of the project's components are covered in the same initial advice statement and terms of reference for the EIS.
Read more about the New Acland Coal Mine Stage 3 Expansion Project.
Environmental impact statement (EIS) process
Date | Activity |
---|---|
19 December 2008 | Coordinator-General's report on Wetalla Water Pipeline Project EIS ( 755 KB) released. |
31 October 2008 | Wetalla Water Pipeline Project supplementary EIS submitted. To obtain a copy, contact the proponent. |
12 July 2008 to 15 August 2008 | Public consultation on Wetalla Water Pipeline Project EIS.
|
26 March 2008 | Project not deemed a controlled action by Commonwealth Minister for the Environment. |
24 October 2007 | Terms of reference for EIS ( 575 KB) released. |
21 July 2007 to 20 August 2007 | Public consultation on draft terms of reference for EIS. |
18 May 2007 | Gazettal of 'significant project' declaration ( 177 KB) |
24 April 2007 | Application, including initial advice statement ( 483 KB), submitted. |
23 April 2007 | Project referred to Commonwealth Minister for the Environment. |
Last updated: 09 Nov 2021