Kidston Pumped Storage Hydro Project
Project overview*
| IAR status | Approved with conditions |
| Description | A 250-megawatt pumped storage hydroelectric power generation facility – the beneficial use of the decommissioned Kidston Gold Mine’s upper and lower pits. |
| Proponent | Genex Power Limited |
| Location/s | Kidston, Queensland approximately 280 km north-west of Townsville. Map |
| Local government/s | Etheridge Shire Council |
| Investment | $777 million |
| Key features | The project would act as a natural battery storage, allowing energy to be stored and harnessed on demand and includes the following components:
|
| Expected completion | 2025 |
| Jobs |
|
IAR process
| Date | Activity |
|---|---|
| 27 April 2021 | Coordinator-General’s report on project change ( |
| 24 September 2019 | Coordinator-General correspondence to Genex Power Limited ( |
| 22 May 2019 | Coordinator-General correspondence to Genex Power Limited ( |
| 5 April 2019 | Coordinator-General’s report on the IAR ( |
| 28 March 2019 | The Coordinator-General accepted the draft IAR as the final IAR. Impact assessment report ( Supplementary information to the IAR ( IAR sections, submitted:
|
| 25 March 2019 | The Coordinator-General accepted the draft IAR as the final IAR. The evaluation stage has commenced. |
| 11 January 2019 | The proponent lodged a draft IAR. |
| 28 September 2018 | Gazettal ( |
| 28 September 2018 | Application, including initial advice statement submitted. |
Read more about the IAR process.
* Project information supplied by proponent and subject to change.
Last updated: 06 Aug 2024