Olive Downs Project
Project overview*
EIS status | Approved with conditions |
Description | Greenfield metallurgical coal mine with a yield of up to 15 million tonnes of product coal per annum for steel production. |
Proponent | Pembroke Olive Downs Pty Ltd. |
Location/s | Approximately 40 km south-east of Moranbah. Map |
Local government/s | Isaac Regional Council. |
Investment | $1b |
Key features |
|
Construction start date |
|
Jobs |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
Date | Activity |
---|---|
13 May 2019 | Coordinator-General’s report on the final EIS released (![]() |
13 May 2019 | The Coordinator-General accepted the draft EIS as the final EIS. |
21 March 2019 | The proponent lodged a revised draft EIS. |
12 December 2018 | Additional information for the EIS requested by the Coordinator-General. |
30 November 2018 |
Coordinator-General stated a new project declaration lapse date of 27 September 2019 |
10 September 2018 to 10 October 2018 |
Draft EIS public consultation |
28 June 2017 | Terms of reference for EIS (![]() |
08 April 2017 to 12 May 2017 | Draft terms of reference (![]() |
03 March 2017 | Commonwealth Minister for the Environment decided the project is a 'controlled action'.
![]() |
17 February 2017 | Gazettal (![]() |
24 January 2017 | Project referred to Commonwealth Minister for the Environment. |
20 January 2017 | Application, including initial advice statement (![]() |
Media releases
- Read the Ministerial media statement - 6 September 2018
- Read the Ministerial media statement - 6 April 2017
- Read the Ministerial media statement - 17 February 2017
Further information
Last updated: Friday, Jun 7, 2019