Project overview*

EIS statusApproved with conditions
DescriptionA two-way 94 kilometre pipeline that can move 130 megalitres per day between the Gold Coast, Logan and Brisbane.
ProponentSouthern Regional Water Pipeline Company Pty Ltd (trading as LinkWater Projects)
Location/sCameron's Hill to Molendinar, Queensland. Map
Local government/sIpswich, Brisbane, Logan and Gold Coast City Councils and Scenic Rim Regional Council
Key features
  • four pump stations
  • two balance tanks
  • microtunnels
  • constructed over 12 elevated crossings, including one over the Brisbane River

* Project information supplied by proponent and subject to change.

Completion of project

The project was completed in November 2008.