Linc Energy Underground Coal Gasification
Project overview*
EIS status | 'Significant project' declaration lapsed |
Description | Underground coal gasification (UCG) operation |
Proponent | Linc Energy Ltd |
Location/s | Linc Energy's mining and exploration tenements, 20 km south-west of Chinchilla, southern Queensland. |
Local government/s | Western Downs Regional Council |
Key features |
|
* Project information supplied by proponent and subject to change.
'Significant project' declaration lapsed
As the proponent's environmental impact statement (EIS) had not been completed by the extended deadline of 30 June 2012, the 'significant project' declaration lapsed.
Environmental impact statement (EIS) process
Date | Activity |
---|---|
30 June 2012 | 'Significant project' declaration lapsed. |
19 November 2009 | Period for submission of EIS extended to 30 June 2012, to allow the feasibility and sustainability of the UCG industry to first be assessed. |
19 November 2007 | Terms of reference for EIS ( 1.49 MB) released. |
25 August 2007 to 24 September 2007 | Public consultation on draft terms of reference for EIS. |
10 August 2007 | Project deemed a controlled action by Commonwealth Minister for the Environment. |
12 July 2007 | Project referred to Commonwealth Minister for the Environment. |
25 May 2007 | Gazettal of 'significant project' declaration ( 74 KB) |
6 November 2006 | Application, including Initial advice statement ( 527 KB), submitted. |
Last updated: 16 Mar 2023