Skip to content

What is the next step in the EIS process?

The Coordinator-General has reviewed the submissions received on the Inland Rail – Calvert to Kagaru draft EIS and has decided additional information is required from ARTC.

Additional information has been sought in several key areas including, but not limited to noise and vibration, traffic and transport, stakeholder engagement, environmental values, flooding, groundwater, economic assessment, social impact and air quality.

ARTC will be providing a written response to the Coordinator-General addressing the submissions received on the draft EIS as part of the revised draft EIS.

The Coordinator-General also decided the revised draft EIS will be publicly notified, and the community will be invited to have their say on the updated information in the revised draft EIS.

Last updated: 09 Nov 2021