Project change application 8 - Changes to the project footprint and changes to the imposed conditions 2020

DateActivity
21 December 2020 Coordinator-General’s amendment report released, correcting clerical errors identified in the change report dated 19 November 2020.
19 November 2020 Coordinator-General's report on project change released, approving the change (as amended 21 December 2020).
2 November 2020

Proponent submitted additional information:

5 September 2020 to 2 October 2020

Public consultation of project change application

Volume 1 – Request for project change 8 application

Volume 2 – Cross River Rail Design Drawings:

Drawing index and locality plans:

General arrangement drawings:

General construction site plans:

Long section drawings

Property impact drawings:

Station drawings

Tunnel and portal drawings

Volume 3 - technical reports

18 August 2020 Proponent’s request for project change application submitted.