Project changes
Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Cross River Rail project.
Request for project change application 9 – Southern Portal Area 2020
Request for project change application 8 - Changes to the project footprint and changes to the imposed conditions 2020
Project change application 7 – Design refinements and condition changes 2020
Project change application 6 – temporary change of certain work hours 2020
Date | Activity |
---|---|
5 June 2020 | The Coordinator-General advised the proponent that Imposed Condition 10A ceases to have effect. |
7 May 2020 | Coordinator-General's report on project change ( |
7 May 2020 | The Coordinator-General decided not to publicly notify the proponent’s change application. |
29 April 2020 | Proponent’s change application submitted ( |
Project change application 5– Condition change (hours of work) 2019
Date | Activity |
---|---|
4 October 2019 | Coordinator-General's report on project change ( |
3 October 2019 | The Coordinator-General decided not to publicly notify the proponent’s change application. |
23 September 2019 | Proponent’s change application submitted ( |
Project change application 4 – Whole of project refinements 2019
Project change application 3 – Roma Street demolition works
Date | Activity |
---|---|
14 March 2019 | Coordinator-General's report on project change ( |
4 March 2019 | Proponent submitted revised information: Roma Street demolition works updated traffic assessment technical note ( |
1 December 2018 to 21 December 2018 | Public consultation of project change application.
|
19 November 2018 | Proponent's change application submitted. |
Project change application 2 – Temporary Roma Street Coach Terminal
Date | Activity |
---|---|
31 August 2018 | Coordinator-General's report on project change (![]() |
23 August 2018 | Proponent submitted revised information: |
3 August 2018 | Proponent submitted revised information: |
17 July 2018 | The Coordinator-General decided not to publicly notify the proponent's change application. |
28 June 2018 | Proponent's change application submitted: |
Project change application 1 – Whole of project
Last updated: Wednesday, Jan 13, 2021