Project change application 4 – Whole-of-project refinements 2019

DateActivity
26 June 2019 Coordinator-General’s report on project change (2 MB) released, approving the change
21 June 2019

Proponent submitted additional information:

20 May 2019 to 14 June 2019

Public consultation of project change application.

Volume 1 - Request for project change 4 application (40 MB)

Volume 2 - Design drawings:

Drawing index and locality plans

General arrangement drawings:

Long section drawings (3 MB)

Station drawings (7 MB)

Tunnel and portal drawings (23 MB)

Property impact drawings:

General construction site plan drawings:

Volume 3 - Technical reports (86 MB)

1 May 2019 Proponent's change application submitted.