Skip to content

Project change application 1 – Whole of project

DateActivity
9 June 2017 Coordinator-General's report on project change (PDF icon 1.5 MB) released, approving the change.
3 April 2017 to 21 April 2017

Extension to public consultation on project change application.

Amended Volume 3 – Cross River Rail design diagrams – All documents not listed here that were subject to consultation over the period 25 February 2017 and 27 March 2017 remain unaltered:

31 March 2017 Coordinator-General decided to extend the public consultation period.
25 February 2017 to
27 March 2017

Public consultation on project change application.

Volume 1 – Request for project change (PDF icon 34.4 MB)

Volume 2 – Draft outline environmental management plan (PDF icon 3 MB)

Volume 3 – Cross River Rail design drawings – sections

Volume 4 – Technical reports (PDF icon 28.6 MB)

5 December 2016 Proponent's change application submitted.