If approved, when will the project be constructed?
IRPL anticipates construction will occur over four years commencing in 2029 to 2033. The below stages precede construction:
- 2025 – 2026 Environmental approvals
- Late 2025 to 2028 Property acquisition, design refinement, early works and detailed design (including consultation with landowners).
Commissioning and operation are expected from 2033 onwards.