Esmeralda Graphite project
Project overview*
EIS status | EIS active |
Description | Greenfield graphite mine and processing plant, extracting up to 3.5 million tonnes per annum of ore to produce approximately 25 million tonnes of graphite concentrate over a 50 year project life. |
Proponent | Qld Aus Graphite Pty Ltd |
Location/s | 70 kilometres south of Croydon, Queensland. Map |
Local government/s |
|
Investment | $666.4 million capital expenditure |
Key features |
|
Construction start date | 2027 |
Jobs |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
Date | Activity |
---|---|
Currently | Draft Terms of Reference for EIS being prepared |
11 July 2025 | Gazettal (![]() |
2 July 2025 | Application, including initial advice statement ( |
23 June 2025 |
Australian Minister for the Environment and Water decided the project is not a ‘controlled action’ ![]() |
Media releases
Further information
Last updated: 11 Jul 2025