Project changes - South of the Embley (Amrun)
Since the publication of the Coordinator-General's report on the EIS, RTA Weipa Pty Ltd has applied for the following changes to the South of the Embley (Amrun) project.
Project change application 4 – Accommodation term and location
| Date | Activity |
|---|---|
| 3 November 2015 | Coordinator-General's report on project change ( |
|
14 October 2015 to 28 October 2015 | Project change application ( |
| 28 September 2015 | Proponent's project change application submitted. |
Project change application 3 – Infrastructure facilities and volume and disposal of dredge spoil
| Date | Activity |
|---|---|
| 18 September 2015 | Coordinator-General's report on project change ( |
| 15 September 2015 | Proponent's project change application ( |
Project change application 2 – General conditions
| Date | Activity |
|---|---|
| 21 November 2013 | Coordinator-General's report on project change ( |
| 30 August 2013 | Proponent's project change application ( |
Project change application 1 - Social conditions
| Date | Activity |
|---|---|
| 1 October 2013 | Coordinator-General's report on project change ( |
| 30 August 2013 | Proponent's project change application ( |
Last updated: 16 Mar 2023