Project overview*
| EIS status | Approved with conditions |
| Description | Integrated liquefied natural gas (LNG) project. |
| Proponent | Queensland Gas Company (QGC), a wholly owned subsidiary of the Shell. |
| Location/s |
|
| Local government/s |
|
| Key features |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| 20 June 14 | The Coordinator-General extended the currency period for the EIS Evaluation Report from 24 June 2014 to 23 June 2016. |
| 22 October 2010 | Commonwealth Minister for the Environment's approval of 'controlled action', subject to conditions. |
| 23 June 2010 | Coordinator-General's report on EIS ( |
| 10 February 2010 to 10 March 2010 | Public consultation on supplementary EIS (SEIS)
|
| 29 August 2009 to 19 October 2009 | Public consultation on EIS
|
| 26 May 2009 | Terms of reference ( |
| 1 November 2008 to 12 December 2008 | Public consultation on draft terms of reference for EIS. |
| 15 September 2008 | Project deemed a 'controlled action' by Commonwealth Minister for the Environment. |
| 18 August 2008 | Project referred to Commonwealth Minister for the Environment. |
| 4 July 2008 | Gazettal of 'significant project' declaration ( |
| 3 June 2008 | Application, including initial advice statement ( |
Read more about the EIS process.
Social impact management plan
As part of its EIS, QGC prepared a social impact management plan.
Project changes
Since the publication of the Coordinator-General's report on the EIS, QGC has applied for changes to the project.
Further information
For more information, visit the Queensland Curtis LNG project web page.