Project changes
Since the publication on the Coordinator-General's report on the EIS, New Acland Coal Pty Ltd has applied for the following changes to the New Acland Coal Mine Stage 3 project.
Project change application 4 – amendment to stated conditions following Land Court (2021) proceedings
Date | Activity |
---|---|
26 May 2022 | Coordinator-General’s report on project change released (![]() |
30 March 2022 | Proponent’s change application submitted (![]() |
Project change application 3 – amendment to stated conditions B3 and H40
Date | Activity |
---|---|
29 September 2020 | Coordinator-General’s report on project change released (![]() |
8 May 2019 | Proponent’s change application submitted (![]() |
Project change application 2 – Train load-out facility
Date | Activity |
---|---|
17 September 2020 | Coordinator-General’s report on project change released (![]() |
22 June 2019 to 21 July 2019 |
Public consultation on project change application (![]() |
24 May 2019 | Proponent’s change application submitted. |
Project change application 1 – Noise
Date | Activity |
---|---|
12 February 2019 | Coordinator-General's report on project change released (![]() |
3 December 2018 | Proponent’s change application submitted (![]() |
Last updated: 16 Mar 2023