What is the process for resumption?
- The landowner/interest holder is contacted and advised of the possible impact of a project on the land.
- A NIR is issued to the landowner/interest holder.
- An objection may be made in accordance with the process outlined in the ALA.
- In response to an objection, the Coordinator-General will consider all relevant information and determine whetherto discontinue, amend or proceed with the resumption.
- If the Coordinator-General determines the resumption should still proceed, they will make an application to theMinister to take the land.
- A resumption notice will be published in the Queensland Government Gazette.
- The land or interest in land will be assessed by a valuer.
- Managing the compensation process as set out in the ALA (including claim, advance payment, negotiations,settlement).
- The title to the affected land is updated in the Land Titles Registry.
Last updated: 10 Jan 2025