What is the process for resumption?

  • The landowner/interest holder is contacted and advised of the possible impact of a project on the land.
  • A NIR is issued to the landowner/interest holder.
  • An objection may be made in accordance with the process outlined in the ALA.
  • In response to an objection, the Coordinator-General will consider all relevant information and determine whetherto discontinue, amend or proceed with the resumption.
  • If the Coordinator-General determines the resumption should still proceed, they will make an application to theMinister to take the land.
  • A resumption notice will be published in the Queensland Government Gazette.
  • The land or interest in land will be assessed by a valuer.
  • Managing the compensation process as set out in the ALA (including claim, advance payment, negotiations,settlement).
  • The title to the affected land is updated in the Land Titles Registry.