The North Queensland Stadium project is on schedule to be completed in time for the start of the 2020 National Rugby League (NRL) season.

The Design Development stage is now underway after the Schematic Design was completed in August 2017.

Early works are underway on site with the main activity being civil earthworks and roadworks.

Project milestones

Item Date*
Principal Consultant, Audit Programmer and Audit Quantity Surveyor appointed 19 Dec 2016
Schematic Design commenced 4 April 2017
Managing Contractor announced 1 May 2017
Expressions of interest invited for early works packages by Watpac via ICN Gateway 2 June 2017
Letting of work packages by Watpac commenced 21 June 2017
Preparatory site works commenced 13 July 2017
Civil earthworks and roadworks commenced 21 August 2017
Schematic Design completed 23 August 2017
Developed Design complete Late 2017
Early site works complete Early 2018
Commencement of main stadium build Early 2018
Stadium complete Early 2020

* subject to inclement weather events, latent site conditions and other unforeseen issues.