Project overview*

EIS status Approved with conditions
Description A 10,500 megalitre urban and irrigation water supply dam on the Severn River.
Proponent Southern Downs Regional Council
Location/s On the Severn River, 15 km south west of Stanthorpe. Map
Local government/s Southern Downs Regional Council
Investment $113.6 million
Key features
  • dam
  • pipelines linking the dam to the region's existing water treatment plant and, potentially, to irrigation properties
  • access road
Jobs
  • 145 (construction)
  • (Number of operational jobs not specified)

* Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

Date Activity
26 September 2017 The Coordinator-General stated a new lapse date for the Coordinator-General’s EIS evaluation report of 2 October 2018.
11 November 2014 Commonwealth Minister for the Environment's approval of controlled action, subject to conditions. More information
29 September 2014 Coordinator-General's report on EIS released (PDF icon 1.7 MB)
2 April 2014 to 2 May 2014 Additional information to EIS (PDF icon 116 MB) assessed by other government agencies.
7 April 2008 Additional information for the EIS requested by Coordinator-General.
12 January 2008 to
25 February 2008
EIS public consultation.
26 June 2007 Terms of reference for EIS (PDF icon 515 KB) released.
31 March 2007 to
8 May 2007
Draft terms of reference for EIS public consultation.
9 February 2007 Gazettal of 'coordinated project' declaration (PDF icon 187 KB)
3 January 2007 Project deemed a controlled action by Commonwealth Minister for the Environment. More information
20 December 2006 Project referred to Commonwealth Minister for the Environment.
8 September 2006 Application, initial advice statement (PDF icon 3.14 MB), submitted.

Read more about the EIS process.