To help councils realise project benefits for their communities sooner, the department has worked with them to see what could be done to deliver projects sooner. As a result, 14 projects commenced construction four or more weeks ahead of schedule—a cumulative total of 105 accelerated construction weeks.

CouncilProject nameNumber of weeks ahead of schedule
Balonne Shire Council St George Airport Infrastructure Upgrade 9
Blackall-Tambo Regional Council Tambo Sawmill Infrastructure Upgrade 9
Boulia Shire Council Donohue Highway Emergency Landing Strip 11
Boulia Shire Council Boulia Reservoir Upgrade 4
Bundaberg Regional Council Stage One Rubyanna Wastewater Treatment Plant (RWWTP) 13
Burke Shire Council Doomadgee to Burketown Optical Fibre Link Project 11
Carpentaria Shire Council Expansion of the Les Wilson Barramundi Discovery Centre, Karumba 4
Central Highlands Regional Council Carnarvon Gorge Road Upgrade 4
Mackay Regional Council Mackay Regional Sewage Pump Station Resilience Upgrades 5
Mareeba Shire Council Mareeba Wastewater Treatment Plant Upgrade - Treatment Plant Works 4
Rockhampton Regional Council Mount Morgan Sewerage Extension Project 4
Weipa Town Authority Evans Landing Boat Ramp Car Park - Stage 2 13
Western Downs Regional Council Chinchilla Potable Water Treatment Plant Upgrade Stage 1 10
Winton Shire Council Winton Shire Geothermal Power Generation 4
13 councils 14 projects 105 weeks

In addition, Cardno has been commissioned to identify opportunities to accelerate the delivery of five high-value projects:

  1. Port Douglas Water Supply Reservoir – Douglas Shire Council
  2. Bromelton State Development Area Stage 1 Trunk Watermain – Scenic Rim Regional Council
  3. Moranbah Resource Recovery Centre Replacement Project – Isaac Regional Council
  4. Roma Flood Mitigation Project - Stage 2 – Maranoa Regional Council
  5. Ravenshoe Wastewater Treatment Plant Upgrade – Tablelands Regional Council

This work is still underway and will accelerate the construction schedule of each of these projects and, importantly, will create a valuable resource to be used in guidance material for Round 3 of the program.