Project overview*

EIS status EIS active
Description Greenfield metallurgical coal mine with a yield of up to 15 million tonnes of product coal per annum for steel production.
Proponent Pembroke Olive Downs Pty Ltd.
Location/s Approximately 40 km south-east of Moranbah. Map
Local government/s Isaac Regional Council.
Investment $1b
Key features
  • open-cut metallurgical coal mine
  • coal handling and preparation plant
  • 18 km rail spur and on site rail loop
  • raw water pipeline connecting to the Eungella pipeline network
  • private access roads
  • electricity transmission line
  • wastewater and sewage treatment plants
Construction start date
  • Olive Downs South domain – 2019
  • Willunga domain - 2027
Jobs
  • 500 (construction)
  • 1000 (operational)

* Project information supplied by proponent and subject to change.

Have your say

Pembroke Olive Downs Pty Ltd has prepared a draft environmental impact statement (EIS) for the Olive Downs project. The Coordinator-General has released the draft EIS for public and government agency comment.

You're invited to comment on the draft EIS, including the project's potential environmental impacts and the effectiveness of measures proposed to manage those impacts. The Coordinator-General will consider your submission as part of his evaluation of the project's environmental impacts.

Read and make a submission on the draft EIS. Submissions close at 5 pm on 10 October 2018.

Environmental impact statement (EIS) process

Date Activity
10 September 2018 to 10 October 2018

Draft EIS public consultation

28 June 2017 Terms of reference for EIS (PDF icon 316 KB) released
08 April 2017 to 12 May 2017 Draft terms of reference (PDF icon 778 KB) for EIS public consultation
03 March 2017 Commonwealth Minister for the Environment decided the project is a 'controlled action'. More information
17 February 2017 Gazettal (PDF icon 239 KB) of 'coordinated project' declaration.
24 January 2017 Project referred to Commonwealth Minister for the Environment.
20 January 2017 Application, including initial advice statement (PDF icon 6.4 MB) , submitted.

Media releases

Further information

Read more about the EIS process.