Since the publication of the Coordinator-General's report on the EIS, Australia Pacific LNG has applied for the following changes to the Australia Pacific LNG Project.

Project change application 6 – Imposed Conditions (General)

Date Activity
21 June 2016 Coordinator-General’s report on project change (PDF icon 824 KB).
13 May 2016 Proponent's project change application (PDF icon 9 MB) submitted.

Project change application 5 – Social

Date Activity
29 September 2015 Coordinator-General's report on project change (PDF icon 5.2 MB) released, approving the change.
16 September 2015 Proponent's project change application (PDF icon 6.5 MB) submitted.

Project change application 4 – General Audit and LNG Facility Operational Environmental Management Plan

Date Activity
28 October 2014 Coordinator-General's report on project change (PDF icon 737 KB) released, approving the change.
2 October 2014 Proponent's project change application (PDF icon 1.7 MB) submitted.

Project change application 3 – CSG Industry Monitoring Group

Date Activity
29 October 2013 Coordinator-General's report on project change (PDF icon 801 KB) released, approving the change.
18 September 2013 Proponent's project change application (PDF icon 517 KB) submitted.

Project change application 2 – Alignment of reporting conditions to SIA Guidelines

Date Activity
29 October 2013 Coordinator-General's report on project change (PDF icon 803 MB) released, approving the change.
18 September 2013 Proponent's project change application (PDF icon 121 KB) submitted.

Project change application 1 - Local content strategy

Date Activity
27 March 2013 Coordinator-General's report on project change (PDF icon 1.04 MB) released, approving the change.
25 March 2013 Proponent's project change application (PDF icon 380 KB) submitted.

Read more about project changes.