If the Governor in Council approves the compulsory land acquisition, a resumption notice is published in the Queensland Government Gazette (a copy of the notice is sent to all interested parties).

More information

On the date the notice is published, the Coordinator-General becomes the owner of the land (or easement).

Anyone else's interest in the land converts to a right to claim compensation.

All other interests (e.g. leases, easements, and mortgages) are discharged.

Vacating the land

At any time following the publication of the resumption notice, the Coordinator-General can take possession of the property acquired.

If the Coordinator-General does not require the land immediately, the date of vacant possession of the property can be negotiated.

If an easement is resumed, the Coordinator-General may begin using the easement from the date of the notice. The Coordinator-General does not need vacant possession of an easement.

Construction

Once the land has been resumed, the Coordinator-General has the right to access the land (or easement) to construct any proposed infrastructure.

Construction can proceed before compensation is paid.