Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Gladstone LNG Project.

Read more about project changes.

Project change application 5 – Social

Date Activity
13 May 2015 Coordinator-General's report on project change (PDF icon 706 KB) released, approving the change.
23 January 2015 Proponent's project change application (PDF icon 923 KB) submitted.

Project change application 4 – Liquefied Natural Gas (LNG) Train 3

Date Activity
14 May 2014 Coordinator-General's report on project change (PDF icon 170 KB) released, approving the change.
28 May 2014 Proponent's project change application (PDF icon 471 KB) submitted.

Project change application 3 – audit conditions

Date Activity
9 March 2014 Coordinator-General's report on project change (PDF icon 838 KB) released, approving the change.
3 January 2014 Proponent's project change application (PDF icon 728 KB) submitted.

Project change application 2 – Increase in pipe transport

Date Activity
5 November 2013 Coordinator-General's report on project change (PDF icon 136 KB) released, approving the change.
9 October 2013 Proponent's project change application (PDF icon 2.14 MB) submitted.

Project change application 1 - Local industry participation plan

Date Activity
27 March 2013 Coordinator-General's report on project change (PDF icon 743 KB) released, approving the change.